Trent Tresch disassembling the HVAC frame, SAM at B2

The work at SAM continues, each day one more item checked off the list. We are nearing the point at which deconstruction gives way to construction, where our effort to break is instead to rebuild. This week Trent and Kai lowered the massive, welded I-beam platform which held the even more massive heat exchanger. Trent remove those bolts that would turn, cut the others, and disassemble the frame.

Cameron removed a complex array of wiring and conduit from the front porch of the test module, the light fixtures yet filled with water from the last rain. The heavily cracked paint was ground and sanded to remove anything lose, the edges feathered, then secured with an exterior metal primer.

Lower Test Module prepared, SAM at B2 Kai Staats painting SAM at B2

Cameron Smith removing old conduit, SAM at B2 Trent Tresch disassembling the HVAC frame, SAM at B2